Aspen School District

2006-2007 Bond Program

 
 Project Name: Aspen School District Bond Program

 

This $33 million project includes a 111,500 sf Replacement Middle School, a 5-classroom addition and remodel to the Elementary School, and some improvements to the District Theater.  The Elementary School addition will match the existing building in terms of layout and appearance.  The Middle School will be a new design based on the concepts of sustainabilty and energy efficiency.  The team is working to obtain LEED certification for this building. 

The Elementary School addition started on June 5th and is scheduled to be complete before Christmas of 2006.  The Replacement Middle School also started June 5th and is scheduled to be complete in the fall of 2007.

 

Resource
Integrated Construction Solutions - Owner's Representative
GE Johnson Construction Company
Hutton Ford Architects
Studio B Architects
Aspen School District
 Add new item
Middle School Completed 6 weeks early and under budget!
by David Detwiler
 12/7/2007 11:42 AM
Due to the hard work of all involved, we were successful in accellerating the schedule to complete the new MS 6 weeks early to allow the kids to start school in the new building rather than the old building as originally planned. 
 
Elementary School Opens To Students Early!
by David Detwiler
 1/24/2007 11:13 AM
On January 3, 2007 the new Classroom Addition at the Elementary School was approved for occupancy, two weeks ahead of schedule.  After final move-in over the winter break, the classrooms were ready for students on the morning of January 8th when...
 